During Outdoor Week (2nd-10th November) the following jobs were
progressed:
- Cutting down wobbly trees in the Dolgoch Woods area and clearing up the
arisings from the storms of the previous week.
- A replacement drain at Fach Goch and relaying 6 lengths of track.
- Concreting the West Carriage Shed floor from the Paint Shop doors to the
side door by the blockpost.